Current Projects

Three New Elite 60ft Houseboats – 

Two of the new boats are at a similar stage, almost mirroring each other on days. They have both had their underfloor heating installed, electrical and plumbing rough in, windows have been installed and the exterior cladding is going on.

IMG_1676 IMG_1789 

DSC_0014  DSC_0017

The third boat build has had its pontoons fabricated and the floor joists completed

pontoons 2  pontoon DSC_0009

 

 

Gone Mad Renovation

Gone Mad has had extensive fibreglass repairs, is in the process of having a custom hardtop fabricated and fitted.